Officer Decisions (archive)
Head of Highways, Capital Development and Waste Management - Meg Booth
Upottery Primary School – Water Penetration Remedial Works
Approved
£26,000 has already been approved for this project at Upottery Primary School.
Following a tender process, a further £8,000 is required to allow this scheme to proceed. The additional funding is due to market forces and this scheme is still considered to represent value for money. This should be phased £5,000 in 2017/18 and £3,000 in 2018/19 and will be funded from savings on the roofing panes project at Upottery Primary.
None
None
A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk